1.Excavation Works
2.Subgrade Filling Works
3.Road Crossing Duct Works
4.Production of Crushing Materials i.e. Aggregated and Powder
5.Road Crossing Duct Works
6.Transportation of Excavated Material
7.Total Cut & Fill Quantity so far is 1,101,000.00 meter cube.