1.Supply and Laying of Subgrade and Subbase Material
2.Supply and Installation of Curb stones including concrete support
3.Supply and Laying of Prime Coat and Base Course – Class B
4.Supply and Laying of Tack Coat and Wearing Course – PMB
5.SupplyInstallation of QNBN Telecom & UGN Ducts,
6.Excavation and Formation for QNBN Lines
7.Bedding, Supply and Laying of QNBN Lines, Surrounding, Supply and Installation of Waring Tapes and Backfilling & Compaction Works
8.Installation and Connection of JRC14 Manholes including the Extension of JRC Manhole Walls
9.Testing Works for QNBN Lines for Concerned Authority Approval.